TIELCO OFFICIALS CONDUCTED SITE INSPECTION ON ONGOING SITIO ELECTRIFICATION PROJECTS


TIELCO General Manager Dennis L. Alag together with Engineering and COM Department Managers Engr. Amante S.Jandoc Jr. and Fred F. Siscar conducted site visit to the ongoing construction of distribution line along the road network in Sitio Canlumay, Bgy. Tumingad to Sitio Aurora , Bgy. Patoo in the town of Odiongan, Romblon. The construction of line, targets the electrification of fifty three (53) unenergized households along the road network and specifically will cover the area of BAPA Agcalape. The projects requires about 84 poles to reach the target households.
 
The project was funded by the Sitio Electrification Program of the goverment which fund was coursed thru the National Electrification Administration (NEA)and downloaded to TIELCO for implementation.
It could be recalled that TIELCO was allocated by the NEA with funds for the electrification projects in nine (9) sitios for CY 2021.